Great start on El Llanito, Nicaragua water supply project

We are here, doing well. Community is going faster than we anticipated. 167 people came to kickoff meeting that CAPS (legally recognized water committee) set agenda for and ran very effectively.


We broke ground on the well support building foundation excavation and for the two pressure break tanks. We staked and marked the route for the pipeline. 


Today over 100 people started at 6 AM excavating for the pipeline.

Forms for pressure break tanks were constructed.


Here are a few photos.